| | | | | | | | ITEM/TOPIC: Construction Contract for a new picnic shelter at Donovan Park
|
| | | | | | | | BACKGROUND: The project is included in the 2016 RETT budget. The town received two bids for the project. The low bid by R.A. Nelson is within the existing budget. With approval, work will begin in mid-September with anticipated completion by mid-November.
|
| | | | | | | | STAFF RECOMMENDATION: Staff recommends approval of the Construction Agreement
|
|