Item Coversheet

VAIL TOWN COUNCIL AGENDA MEMO

ITEM/TOPIC:   Reconsideration of the Public Works Shop Yard Expansion Retaining Wall and Utilities Project Award 

PRESENTER(S):   Greg Hall, Public Works Director

ACTION REQUESTED OF COUNCIL:   After hearing presentation, reconfirm, reconsider and provide direction on the project. 

BACKGROUND:   Public Works Director will present additional information about project options for the Public Works Shop Yard expansion related to the retaining wall and utilities. Council approved an agreement with Hyder Construction for $4.6 M on May 5. With some additional information to be presented about the project, Town Council will be asked to reconfirm, reconsider and provide direction on the project in light of this information. 

ATTACHMENTS:
Description
Memo Public Works Shop Project