| | | | | | | | VAIL TOWN COUNCIL AGENDA MEMO
|
| | | | | | | | ITEM/TOPIC: Red Sandstone Elementary School Parking Structure Update
|
| | | | | | | | PRESENTER(S): Greg Hall Director of Public Works and Transportation
|
| | | | | | | | ACTION REQUESTED OF COUNCIL: . The staff has requested the Town Council address the following:
- Authorize the Town Manager to enter into a pre-construction contract with Haselden Construction in a form approved by the Town Attorney in the amount of $257,500
- Amend the 2017 supplemental budget for the design and construction of the south I 70 improvements by $287,500 to be funded by Vail Reinvestment Authority
|
| | | | | | | | BACKGROUND: The Town of Vail and the Eagle County School District are working together to jointly construct a four-level 160 car parking structure on the current Red Sandstone School site. The work will include extensive site work to establish a loop road around the parking structure to allow access to each level while at the same time provide a one-way loop road for school drop off and pick up.
|
| | | | | | | | STAFF RECOMMENDATION: Staff recommends the Town Council continue to pursue the four-level structure. In addition, the Town Council should take action on the items below:
- Authorize the Town Manager to enter a pre-construction contract with Haselden Construction in a form approved by the Town Attorney in the amount of $257,500
- Amend the 2017 supplemental budget for the design and construction of the south I-70 improvements in the amount of $287,500 to be funded by Vail Reinvestment Authority.
|
|